East End News

Phases for Forsyth & Skinker Intersection Work

In an effort to enhance pedestrian, bicycle and vehicle safety, Washington University is working with Forest Park and the city of St. Louis to improve the intersection at Forsyth & Skinker.

  • Through traffic will be maintained at all times during construction
  • Be prepared for traffic interruptions and lane closures, as well as pedestrian and bicycle rerouting

See below diagrams for impacts and approximate dates (weather dependent).

Phase 1

June 13, 2018 – July 20, 2018

Diagram of intersection updates being made in the Summer of 2018 at Forsyth Boulevard and North Skinker Boulevard

Phase 2A

June 23, 2018 – August 22, 2018

Diagram of intersection updates being made in the Summer of 2018 with Construction Area, Lane Closure, Shared Bike Path, and Pedestrian Paths marked

Phase 2B

August 1, 2018 – August 10, 2018

Diagram of intersection updates being made in the August 2018 at Forsyth Boulevard and North Skinker Boulevard showing the Construction Areas and Lane Closures

Phase 3A

August 23, 2018 – September 6, 2018

Diagram of intersection updates being made in the Summer of 2018 with Construction Area, Lane Closure, Shared Bike Path, and Pedestrian Paths marked

Phase 3B

September 6, 2018 – September 28, 2018

Diagram of intersection updates being made in the August 2018 at Forsyth Boulevard and North Skinker Boulevard showing the Construction Areas and Lane Closures